Slipper Launch Project


People often ask me how far into the project I am, so I've prepared a very rough project outline and timescale.
All I'll say is "Don't try and hold me to it. After all, this is meant to be a hobby..."

Project Start:
Projected Finish:
Sat 01 Nov'03
Tue 31 Oct '06


Tasks

ID
Task Name
DurationStartFinish% Complete
1
Slipper Launch construction
795 daysSat 01 Nov '03Tue 31 Oct '0633%
2
Preliminary hull
305 daysSat 01 Nov '03Fri 31 Dec '0492%
3
Scarfing
2 monthsSat 01 Nov '03Fri 26 Dec '03100%
4
Lofting
0.5 monthThu 01 Jan '04Wed 14 Jan '04100%
5
Panel machining
1 monthThu 15 Jan '04Wed 11 Feb '04100%
6
Stitching
1.75 monthsThu 12 Feb '04Wed 31 Mar '04100%
7
Bulkhead machining & bonding
6.55 monthsThu 01 Apr '04Thu 30 Sep '04100%
8
Filleting
1.05 monthsFri 01 Oct '04Sun 31 Oct '04100%
9
Preparation and move Hull
1.1 monthsMon 01 Nov '04Tue 30 Nov '04100%
10
Workshop upgrade
23 daysWed 01 Dec '04Fri 31 Dec '04100%
11
Transom
32 daysSat 01 Jan '05Mon 14 Feb '05100%
12
Pattern
0.55 monthSat 01 Jan '05Sun 16 Jan '05100%
13
Manufacture
0.55 monthMon 17 Jan '05Mon 31 Jan '05100%
14
Fit and Bond
0.5 monthTue 01 Feb '05Mon 14 Feb '05100%
15
Sheer
11 daysTue 15 Feb '05Mon 28 Feb '05100%
16
Scarf
7 daysTue 15 Feb '05Tue 22 Feb '05100%
17
Bond to hull
4 daysWed 23 Feb '05Mon 28 Feb '05100%
18
Deck beams
43 daysTue 01 Mar '05Thu 28 Apr '05100%
19
Laminate deck beams
1 monthTue 01 Mar '05Mon 28 Mar '050%
20
Forward hatch
1 monthTue 01 Mar '05Mon 28 Mar '050%
21
Bond to hull
1 monthFri 01 Apr '05Thu 28 Apr '050%
22
Roll over
23 daysSun 01 May '05Tue 31 May '05100%
23
Fixture preparation
11 daysSun 01 May '05Sun 15 May '05100%
24
Rol over
11 daysTue 17 May '05Tue 31 May '05100%
25
Sheath hull
22 daysWed 01 Jun '05Thu 30 Jun '05100%
26
Clean up underside
6 daysWed 01 Jun '05Wed 08 Jun '05100%
27
Bond second skin
11 daysThu 09 Jun '05Thu 23 Jun '05100%
28
Sheath
5 daysFri 24 Jun '05Thu 30 Jun '050%
29
Keel
47 daysFri 01 Jul '05Wed 31 Aug '05100%
30
Buy propeller shaft assy
1 dayFri 01 Jul '05Sat 02 Jul '05100%
31
Laminate keel
18 daysFri 01 Jul '05Sun 24 Jul '05100%
32
Prepare hull
6 daysMon 25 Jul '05Sun 31 Jul '05100%
33
Bond to hull
14 daysMon 01 Aug '05Thu 18 Aug '05100%
34
Sheath
9 daysFri 19 Aug '05Wed 31 Aug '05100%
35
Rudder
23 daysThu 01 Sep '05Fri 30 Sep '050%
36
Buy or fabricate assy
2 daysThu 01 Sep '05Fri 02 Sep '050%
37
Prepare hull
11 daysThu 01 Sep '05Thu 15 Sep '050%
38
Fit to hull
12 daysFri 16 Sep '05Fri 30 Sep '050%
39
Roll over
23 daysSat 01 Oct '05Mon 31 Oct '050%
40
Fixture preparation
11 daysSat 01 Oct '05Fri 14 Oct '050%
41
Rol over
12 daysSat 15 Oct '05Mon 31 Oct '050%
42
Engine
44 daysTue 01 Nov '05Sat 31 Dec '050%
43
Mounting beams
11 dayTue 01 Nov '05Tue 15 Nov '050%
44
Fuel cell
11 daysWed 16 Nov '05Wed 30 Nov '050%
45
Battery
11 daysThu 01 Dec '05Thu 15 Dec '050%
46
Cooling
11 daysFri 16 Dec '05Sat 31 Dec '050%
47
Deck
66 daysSun 01 Jan '06Fri 31 Mar '060%
48
Cover boards
23 daysSun 01 Jan '06Tue 31 Jan '060%
49
Infill boards
20 daysWed 01 Feb '06Tue 28 Feb '060%
50
Forward hatch
11 daysWed 01 Mar '06Wed 15 Mar '060%
51
Cockpit surround
12 daysThu 16 Mar '06Fri 31 Mar '060%
52
Internal fit out
66 daysSat 01 Apr '06Fri 30 Jun '060%
53
Panelling
44 daysSat 01 Apr '06Wed 31 May '060%
54
cockpit floor
11 daysThu 01 Jun '06Thu 15 Jun '060%
55
Upholstery
11 daysFri 16 Jun '06Fri 30 Jun '060%
56
Controls
22 daysSat 01 Jul '06Mon 31 Jul '060%
57
Electronics
22 daysSat 01 Jul '06Mon 31 Jul '060%
58
steering
22 daysSat 01 Jul '06Mon 31 Jul '060%
59
propulsion controls
22 daysSat 01 Jul '06Mon 31 Jul '060%
60
Moveout
23 daysTue 01 Aug '06Thu 31 Aug '060%
61
Fit engine
43 daysFri 01 Sep '06Mon 30 Oct '060%
62
Launch
1 dayTue 31 Oct '06Tue 31 Oct '060%