Slipper Launch Project
People often ask me how far into the project I am, so I've prepared a very rough project outline and timescale.
All I'll say is "Don't try and hold me to it. After all, this is meant to be a hobby..."
Project Start:
Projected Finish:
Sat 01 Nov'03
Tue 31 Oct '06
Tasks
ID
Task Name
Duration
Start
Finish
% Complete
1
Slipper Launch construction
795 days
Sat 01 Nov '03
Tue 31 Oct '06
33%
2
Preliminary hull
305 days
Sat 01 Nov '03
Fri 31 Dec '04
92%
3
Scarfing
2 months
Sat 01 Nov '03
Fri 26 Dec '03
100%
4
Lofting
0.5 month
Thu 01 Jan '04
Wed 14 Jan '04
100%
5
Panel machining
1 month
Thu 15 Jan '04
Wed 11 Feb '04
100%
6
Stitching
1.75 months
Thu 12 Feb '04
Wed 31 Mar '04
100%
7
Bulkhead machining & bonding
6.55 months
Thu 01 Apr '04
Thu 30 Sep '04
100%
8
Filleting
1.05 months
Fri 01 Oct '04
Sun 31 Oct '04
100%
9
Preparation and move Hull
1.1 months
Mon 01 Nov '04
Tue 30 Nov '04
100%
10
Workshop upgrade
23 days
Wed 01 Dec '04
Fri 31 Dec '04
100%
11
Transom
32 days
Sat 01 Jan '05
Mon 14 Feb '05
100%
12
Pattern
0.55 month
Sat 01 Jan '05
Sun 16 Jan '05
100%
13
Manufacture
0.55 month
Mon 17 Jan '05
Mon 31 Jan '05
100%
14
Fit and Bond
0.5 month
Tue 01 Feb '05
Mon 14 Feb '05
100%
15
Sheer
11 days
Tue 15 Feb '05
Mon 28 Feb '05
100%
16
Scarf
7 days
Tue 15 Feb '05
Tue 22 Feb '05
100%
17
Bond to hull
4 days
Wed 23 Feb '05
Mon 28 Feb '05
100%
18
Deck beams
43 days
Tue 01 Mar '05
Thu 28 Apr '05
100%
19
Laminate deck beams
1 month
Tue 01 Mar '05
Mon 28 Mar '05
0%
20
Forward hatch
1 month
Tue 01 Mar '05
Mon 28 Mar '05
0%
21
Bond to hull
1 month
Fri 01 Apr '05
Thu 28 Apr '05
0%
22
Roll over
23 days
Sun 01 May '05
Tue 31 May '05
100%
23
Fixture preparation
11 days
Sun 01 May '05
Sun 15 May '05
100%
24
Rol over
11 days
Tue 17 May '05
Tue 31 May '05
100%
25
Sheath hull
22 days
Wed 01 Jun '05
Thu 30 Jun '05
100%
26
Clean up underside
6 days
Wed 01 Jun '05
Wed 08 Jun '05
100%
27
Bond second skin
11 days
Thu 09 Jun '05
Thu 23 Jun '05
100%
28
Sheath
5 days
Fri 24 Jun '05
Thu 30 Jun '05
0%
29
Keel
47 days
Fri 01 Jul '05
Wed 31 Aug '05
100%
30
Buy propeller shaft assy
1 day
Fri 01 Jul '05
Sat 02 Jul '05
100%
31
Laminate keel
18 days
Fri 01 Jul '05
Sun 24 Jul '05
100%
32
Prepare hull
6 days
Mon 25 Jul '05
Sun 31 Jul '05
100%
33
Bond to hull
14 days
Mon 01 Aug '05
Thu 18 Aug '05
100%
34
Sheath
9 days
Fri 19 Aug '05
Wed 31 Aug '05
100%
35
Rudder
23 days
Thu 01 Sep '05
Fri 30 Sep '05
0%
36
Buy or fabricate assy
2 days
Thu 01 Sep '05
Fri 02 Sep '05
0%
37
Prepare hull
11 days
Thu 01 Sep '05
Thu 15 Sep '05
0%
38
Fit to hull
12 days
Fri 16 Sep '05
Fri 30 Sep '05
0%
39
Roll over
23 days
Sat 01 Oct '05
Mon 31 Oct '05
0%
40
Fixture preparation
11 days
Sat 01 Oct '05
Fri 14 Oct '05
0%
41
Rol over
12 days
Sat 15 Oct '05
Mon 31 Oct '05
0%
42
Engine
44 days
Tue 01 Nov '05
Sat 31 Dec '05
0%
43
Mounting beams
11 day
Tue 01 Nov '05
Tue 15 Nov '05
0%
44
Fuel cell
11 days
Wed 16 Nov '05
Wed 30 Nov '05
0%
45
Battery
11 days
Thu 01 Dec '05
Thu 15 Dec '05
0%
46
Cooling
11 days
Fri 16 Dec '05
Sat 31 Dec '05
0%
47
Deck
66 days
Sun 01 Jan '06
Fri 31 Mar '06
0%
48
Cover boards
23 days
Sun 01 Jan '06
Tue 31 Jan '06
0%
49
Infill boards
20 days
Wed 01 Feb '06
Tue 28 Feb '06
0%
50
Forward hatch
11 days
Wed 01 Mar '06
Wed 15 Mar '06
0%
51
Cockpit surround
12 days
Thu 16 Mar '06
Fri 31 Mar '06
0%
52
Internal fit out
66 days
Sat 01 Apr '06
Fri 30 Jun '06
0%
53
Panelling
44 days
Sat 01 Apr '06
Wed 31 May '06
0%
54
cockpit floor
11 days
Thu 01 Jun '06
Thu 15 Jun '06
0%
55
Upholstery
11 days
Fri 16 Jun '06
Fri 30 Jun '06
0%
56
Controls
22 days
Sat 01 Jul '06
Mon 31 Jul '06
0%
57
Electronics
22 days
Sat 01 Jul '06
Mon 31 Jul '06
0%
58
steering
22 days
Sat 01 Jul '06
Mon 31 Jul '06
0%
59
propulsion controls
22 days
Sat 01 Jul '06
Mon 31 Jul '06
0%
60
Moveout
23 days
Tue 01 Aug '06
Thu 31 Aug '06
0%
61
Fit engine
43 days
Fri 01 Sep '06
Mon 30 Oct '06
0%
62
Launch
1 day
Tue 31 Oct '06
Tue 31 Oct '06
0%